April 5, 2023 - Schematic Design & Class D Capital & Operational Estimates

have been provided to the City of Dawson for review and direction from council. A summary and presentation were prepared which can be viewed below. The two design options were reflective of the amenities drafted by council and administration at a working group meeting. What has been provided remains conceptual. Once direction is received, consultants will refine and finalize the schematic drawings, after which detailed design would occur, followed by tendering for construction.

  • Council Presentation - Summary of Design and Class D Cost Estimates - Options A & B (April 5, 2023)
  • Schematic Drawings - Options A & B
  • Class D Estimates - Capital, Operational - Options A & B 

In winter 2020-21, a Feasibility Study was undertaken to determine the scale, scope and location of a new recreation centre; estimate the capital costs for different versions of this building, as well as the operational and maintenance costs which may be incurred. These options were shared with the public, and reviewed by administration and council.

It was ultimately decided that Lot 1059 (Base of Dome Road) was the preferred location to build. It was also decided that Option 1 should be pursued at the preferred scale and scope for this building. The plan for Option 1 included a skating rink, two curling sheets, a gymnasium, indoor play space, canteen and office space.

Dawson City Recreation Centre Feasibility Study

The plan for Option 1 can be seen below

 * NOTE: This gives an overview of the major components that are envisioned to be included. The Schematic Design (May-September 2022) will be the initial design, which will refine the size and features included in these spaces, based on a similar scope and scale of the plan provided in the Feasibility Study

Next Steps / Potential Timeline
*Note: This is a best outlook schedule. Delays due to review and approval timelines, funding or environmental approvals, may occur.

  • SCHEMATIC DESIGN (May 2022-May 2023)
    • Refine design of facility components and programming
    • Complete additional data gathering: survey, Geotech, etc.
    • Review existing background data (including previously completed: geotech, ESAs, HRIA, etc.)
    • Complete Preliminary Design Drawings and reporting
    • Class C cost estimate (including capital and O&M, completed by quantity surveyor)
    • Targeted Community engagement
    • Include review of rec facilities that are working well in the North
    • Include consideration for pre-eng components and engage pre-eng. specialist.
    • Detailed review of servicing requirements.
    • Energy modelling.

  • ENVIRONMENTAL APPROVALS (Ongoing)
    • YESAB may be required. Engage consultant at the beginning of schematic design phase. Application to be submitted at the end of Schematic Design
    • Review if Fisheries or Water Board approvals required.

  • FUNDING APPLICATION & APPROVAL (October 2022-May 2023)
    • Federal and YG funding approvals required
    • Development of Service Agreement between CoD and YG.

  • PUBLIC PROCUREMENT FOR DETAILED DESIGN (June 2023-August 2023)
    • RFP to hire detailed design consultant, construction admin and site inspection.

  • DETAILED DESIGN (August 2023-December 2023)
  • CONSTRUCTION TENDER & AWARD (January 2024-April 2024)
  • CONSTRUCTION START (Spring 2025)