December 21, 2023 - Schematic Design, Class C Capital and Operational Estimates
Contractors provided City of Dawson and Yukon Government with new Schematic Design and Class C Capital and Operation Estimates, based on the direction received in April 2023, to include the following amenities: Recreation Office, Skating Rink, Curling Rink, Fitness Centre, Bouldering Wall, Sauna, Gymnasium, Walking Track, Indoor Playground, and concession area. The estimates came in higher than anticipated (approximately $95 million with a 25% +/- differential). A presentation was made to Council on December 5, 2023 with the drawings and cost estimates, that presentation is below.
- Council Presentation - Summary of Design and Class C Cost Estimates - December 2023
Following this presentation, mainly as a result of the cost estimates, Council passed a resolution at Meeting C23-19 Council Direct Administration to develop a work plan for a new recreation centre within the $65 million budget.
Next Steps for this project:
- Project Management Team to meet, discuss options for next steps, and return to City of Dawson Council to discussion and approval. Expect to present at January 16 Council Meeting.
City of Dawson received new schematic drawings, to explore the
- Council Presentation - Summary of Design and Class D Cost Estimates - Options A & B (April 5, 2023)